Penggunaan Metode Jalur Kritis pada Manajemen Proyek (Studi Kasus: PT. Trend Communications International)

Abstrak

Project Management has been an important part of software development projects, therefore the use of technology to endorse effectiveness and efficiency of Project Management is a crucial aspect. PT. Trend Communications Internation (TRENDcom) is a company providing Project Management Office (PMO) service. Their main service is to provide expertise in managing Information Technology projects. One of the big issues they are facing is managing timeline. Late of delivery is caused by people, process and technology reasons. Technology-wise, the absence of application to let project manager and his PMO team the important activities that will cause delay on overall progress as well as the lack of reminder for their due project activities. Using Critical Path Method, an application is developed to address the issues. The application managed to give information of activities in a schedule which has big impact on overall delivery timeline and to provide reminder of due activities.

Author Biographies

Nurvelly Rosanti, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas TeknikErwin Setiawan, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas TeknikAsti Ayuningtyas, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas Teknik

References

Project Management Institute. 2009. Project Management Body of Knowledge (4th Edition). Project Management Institute. Pennsylvania,

USA.

Mosaic Project Services. 2007. The Origins of Modern Project Management. Mosaic Project

Services. Melbourne.

Baker, Samuel L. 2004. Critical Path Method (CPM). (http://hspm.sph.sc.edu/COURSES/J716/CPM/CPM.html, diakses 14 Desember 2014).

De Weck, Olivier. 2012. Critical Path Method (CPM) (ocw.mit.edu/…/MITESD_36F12_Lec02.pdf, diakses 14 Desember 2014).

Sommerville, Ian. 2011. Software Engineering (9th Edition). Pearson. Boston, Massachusettes, USA.

Solichin, Achmad. 2009. Pemrograman Web dengan PHP dan MySQL.

Full PDF : https://journal.uhamka.ac.id/index.php/teknoka/article/view/339/pdf

This web supported by : www.uhamka.ac.id

Leave a comment

Your email address will not be published. Required fields are marked *

cahayapoker cahayaqq slot depo 5k slot thailand link jpslot388 jpslot388 login jpslot388 rtp jpslot388 pkv games bandarqq dominoqq pkv games bandarqq dominoqq https://dollishpolish.bigcartel.com/ Pkv Games Dominoqq Pkv http://westclinic.xsrv.jp/ pkv games login bandarqq login dominoqq login https://128.199.140.43/ https://eamonnmallie.com/ https://paficengkarengtimur.org/ https://pafijp.org/ https://callanwoldeartsfestival.com/ https://sispadu.com/scss/bandarqq/ https://sispadu.com/scss/dominoqq/ https://sispadu.com/scss/pkv-games/ https://usayhello.com/bandarqq/ https://usayhello.com/dominoqq/ https://usayhello.com/pkv-games/ https://admin.snowcarbon.co.uk/bandarqq/ https://admin.snowcarbon.co.uk/dominoqq/ https://admin.snowcarbon.co.uk/pkv-games/ bandarqq dominoqq pkv-games https://final88.app/ https://final88.live/ https://final88.pro/ https://final88.shop https://final88.site/ https://final88.vip/ https://final88.wiki/ https://bandar-qq.it.com/ https://jpslot388.it.com/ https://qiuqiu.it.com/ aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong bandarqq cahayapoker dominoqq jawadomino aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong slot5k depo5k linkslot5k slotonline5k slotresmi jawadomino aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslotaduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong jpslot388 mega+hoki jitujp memberbarupastiwd slot+online slot+5k slot+depo+5k mpogacor88 sbobet slotgacor slotgopay slot+hoki rtp+slot angka+togel+hari+ini ratuslot aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong aduqq bandarqq cahayapoker cahayaqq domino99 dominoqq jawadomino pkvcasino pkvsports pkvslot qiuqiu sakong https://kemetic.app/ https://www.omdigit.com/ cahayapoker cahayaqq jawadomino https://edubag.net/ https://www.tadribmsr.com/ https://globaldevgate.com/ cahayapoker https://balusen.com/ cahaya jawa poker jawa jawabandar jawapkv jawaqiu jawaslot jawasports cahaya cahayabandar cahayapkv cahayaqiu cahayaslot cahayasports poker pokerbandar pokerpkv pokerqiu pokerslot pokersports jawa jawabandar jawaqiu jawaslot jawasports cahaya cahayabandar cahayaqiu cahayaslot cahayasports poker pokerbandar pokerqiu pokerslot pokersports pay4d mpo77 jpslot388 Rajaslot turbox500 ratuslot k200m+login slot+online+gacor situs+slot+gacor demo+slot+gacor slot+gacor+terpercaya situs+slot+terpercaya rtp+slot+gacor+hari+ini link+slot+gacor+hari+ini situs+slot+resmi+dan+terpercaya pay4d mpo77 jpslot388 Rajaslot turbox500 ratuslot k200m+login slot+online+gacor situs+slot+gacor demo+slot+gacor slot+gacor+terpercaya situs+slot+terpercaya rtp+slot+gacor+hari+ini link+slot+gacor+hari+ini situs+slot+resmi+dan+terpercaya pay4d mpo77 jpslot388 Rajaslot turbox500 ratuslot k200m+login slot+online+gacor situs+slot+gacor demo+slot+gacor slot+gacor+terpercaya situs+slot+terpercaya rtp+slot+gacor+hari+ini link+slot+gacor+hari+ini situs+slot+resmi+dan+terpercaya pay4d mpo77 jpslot388 Rajaslot turbox500 ratuslot k200m+login slot+online+gacor situs+slot+gacor demo+slot+gacor slot+gacor+terpercaya situs+slot+terpercaya rtp+slot+gacor+hari+ini link+slot+gacor+hari+ini situs+slot+resmi+dan+terpercaya jawa jawabandar jawaqiu jawaslot jawasports cahaya cahayabandar cahayaqiu cahayaslot cahayasports poker pokerbandar pokerqiu pokerslot pokersports jawa jawabandar jawaqiu jawaslot jawasports cahaya cahayabandar cahayaqiu cahayaslot cahayasports poker pokerbandar pokerqiu pokerslot pokersports jawa jawabandar jawaqiu jawaslot jawasports cahaya cahayabandar cahayaqiu cahayaslot cahayasports poker pokerbandar pokerqiu pokerslot pokersports